Water Resources

Picture This: Magnolia Green Elevated Tank

Timmons Group provided engineering design, permitting and construction administration for Chesterfield County’s newest 2,000,000 gallon elevated composite storage tank which will serve the Magnolia Green Development and surrounding area. The project featured the construction of the 165’ tall water storage tank and 2,500’ of 24” & 30” ductile iron waterline.

The tank was designed utilizing Autodesk Revit software which was used to design the tank in 3D and allow very accurate plans, sections and elevations to be prepared. The 3D model also allowed the creation of renderings for client review meetings.

The project was designed to Chesterfield County’s strict design standards and included a SCADA system with radio communication, lighting protection, cathodic protection system, active tank mixing system, provisions for future cell phone antennas, 24″ double acting altitude valve and bridge crane for altitude valve maintenance.

Design challenges included remediation of the onsite soils which required the use of 168′ geopiers which were 30″ in diameter and 15′ deep. This innovative approach allowed a shallow foundation system to be used for the tank and prevented the need for a deep pile foundation.

Share this post

Share this post

About The Author

Here are some related posts

Picture This: Hardy Elementary School Elevated Tank
Engineering Safe Drinking Water for the Old Oaks Community
The Hidden Backbone of Urban Development: Understanding Dry Utilities
Understanding the Role of a Subsurface Utility Engineering Vacuum Excavator Truck