Project Summary

Timmons Group completed a Phase I ESA for three urban properties totaling 2.275 acres in conjunction with property transfer.  Based on usage and site history, Timmons Group recommended and completed a Phase II ESA to assess the presence of subsurface petroleum contamination.  In addition Timmons Group recommended that the remnant USTs discovered onsite be excavated and removed.  Following the Phase II ESA, Timmons Group recommended source removal as Phase III ESA remediation.  Under the supervision of Timmons Group, over the USTs and over 400 tons of soil were excavated and removed from the site for disposal.